13/06/2026
Regraveling Project on track
The regraveling of the road between Clanwilliam and Calvinia was successfully completed with only minor finishing and flood damage repair work scheduled for completion by the end of July.
The project involved widening the road from 6 metres to 7.5 metres, importing and placing new gravel wearing course material, improving drainage through the installation of new culverts and extensions to existing culverts, and finishing the road surface to improve rideability, durability, and safety.
The work was carried out by the Construction and Concrete team from the northern region of the district, on behalf of the Western Cape Government, demonstrating the exceptional value and expertise that exists within the public sector.
This upgrade forms part of the West Coast District Municipality's ongoing commitment to maintaining a safe and reliable road network for all road users.