09/10/2026
π§ Crews are wrapping up excavation work around the bridge and new cul-de-sacs. In the coming weeks, work will shift to drainage improvements, storm sewer installation, pond excavation, and ramp construction. Pipe installation and gravel placement at the southbound roundabout are also scheduled to begin next week.
Learn more and sign up for updates on the project website: clients.bolton-menk.com/hwy169andcr4/