Here is the schedule of Abernethy Bridge nighttime work for the rest of this week:
* Tuesday (9/15): demolition work in the evening at the OR 43 off-ramp from I-205 south, stopping by midnight. Girder installation from 10 p.m. to 5 a.m. on the northbound side of I-205.
* Wednesday (9/16): demolition work in the evening at the OR 43 off-ramp from I-205 south, stopping by midnight. Girder installation from 10 p.m. to 5 a.m. on the northbound side of I-205.
* Thursday (9/17): demolition work in the evening at the OR 43 off-ramp from I-205 south, stopping by midnight. Girder installation from 10 p.m. to 5 a.m. on the northbound side of I-205.
* Friday (9/18): demolition work in the evening at the OR 43 off-ramp from I-205 south, stopping by midnight. Girder installation from 10 p.m. to 5 a.m. on the northbound side of I-205.