Midland Valley Fire Department

Midland Valley Fire Department Fire Department

Our guys and girls have had a busy few days! 🚒🔥From a structure fire to a brush fire, our crews have been putting in the...
08/26/2026

Our guys and girls have had a busy few days! 🚒🔥

From a structure fire to a brush fire, our crews have been putting in the work to help keep our community safe.

With the dry conditions, we want to remind everyone: if you’re planning to burn outdoors, please use extra caution and have a reliable water source nearby. A small fire can spread quickly.

We’re proud of our crews and thankful for their continued dedication and teamwork. Stay safe, everyone! ❤️🚒

08/17/2026

Send a message to learn more

Was so sad to see the condition of these animals.
07/27/2026

Was so sad to see the condition of these animals.

26 DOGS, 12 CATS, AND 2 BUNNIES RESCUED IN AIKEN COUNTY... MAN ARRESTED FOR ILL TREAMENT OF ANIMALS

Aiken County animal control officials have removed 26 dogs, 12 cats, and two bunnies from a property in the Beech Island area following an ongoing investigation into animal welfare concerns.

On Friday, Aiken County Code Enforcement, with assistance from the Aiken County Sheriff’s Office and Midland Valley Fire Department, responded to the situation at this home on Wall Street.

During the investigation, officials took action to protect the animals and ensure they received proper care.

Joe Clemmons, 61 (pictured), was charged Friday with two counts of ill-treatment of animals under South Carolina law. He is free on bond.

This investigation remains ongoing. Anyone with information regarding this case is asked to contact Aiken County Code Enforcement by emailing:
[email protected]

THE WARRANTS SPELL OUT THE SPECIFIC ALLEGATIONS: https://theaugustapress.com/dogs-cats-bunnies-rescued-from-beech-island-home-after-arrest-for-ill-treatment/

07/20/2026

We are currently having trouble with our phone service. Hope to have it restored soon.

FYI
07/15/2026

FYI

🌁‼️🚨You all wanted to know why Storm Branch Rd bridge has taken so long.
Here is a detailed email from SCDOT with all of that information. Scheduled Completion Summer 2026.
Please share.

Representative Oremus,

Per your request, below are timelines of activities for the Storm Branch Road bridge project. One general reason why this project has taken as long as it has is because we're replacing a failed culvert with a new bridge. Had we been replacing an old bridge with a new bridge in the exact footprint (as was the case with the Vaucluse Road bridge over I-20), this project likely would have progressed much more quickly. The new bridge structure will serve the community for a lifetime.

"Preconstruction" items
Engineering/design, utility relocation, permitting and Right of Way acquisition. There is usually very little activity on site of a project while these items are being done, so some people may become frustrated because they don't see activity on site, all the while these items are being worked as requirements to be completed before construction.

A structural assessment in late October 2023 revealed severe, hidden structural issues. Although the road surface appeared intact, it was closed immediately to protect motorists. The evaluation proved that the existing, undersized culvert was beyond repair. Replacing it with a modern bridge strengthens critical infrastructure and reopens a vital corridor for this community. Furthermore, the new design eliminates the risk of debris buildup, preventing upstream flooding and structural impacts while also reducing future maintenance costs.

Following the initial emergency assessment and closure in October 2023, SCDOT partnered with design consultants in November 2023 to develop a specialized, expedited path forward for design and construction. Between November 2023 and April 2025, our teams worked through several complex, concurrent development phases.

To fit the new, larger bridge structure, Pepper Branch Road had to be realigned. This required extensive additional design and coordination, compared to a more standard, straightforward bridge replacement. The realignment was crucial to provide proper intersection sight distances and safe turning movements.

Because construction requires operating heavy machinery directly within sensitive wetlands and a skewed creek that needed to be realigned, SCDOT had to secure a federal US Army Corps of Engineers general environmental permit. This strict federal oversight is an important construction requirement which ensures the waterway is fully protected during construction and completely restored upon completion.

Right-of-way acquisition normally takes 12 months or more. To accelerate the timeline, the design team fast-tracked the 9 property acquisitions required for the project. Four properties granted immediate construction permission, while five required more lengthy, legal condemnation actions to clear property titles. (The Right of Way acquisition processes are needed to maintain the personal property rights of landowners.)

Additionally, the road realignment resulted in conflicts with existing water, gas, power, communications, fiber optics, TV/cable, and phone lines. Gas, fiber, cable and phone lines were moved at no cost to the project. All utilities had to be moved and completely resolved before bridge construction could begin.

So, from road closure to construction contract letting, the preconstruction portion took about 18 months. Given the amount of preconstruction work required for this project, this is faster than what many similar projects experience.

Construction
After preconstruction, actual construction work could begin:
* 06/25/25 - Project construction contract was Awarded
* 08/07/25 - Pre-Construction Conference was held and Notice to Proceed was issued to contractor
* 08/29/25 - Work Start Date - Installed Permanent Construction Signs
* From 8/29/25 to 11/26/25 - Prime Contractor completed the following:
* Cleared and Grubbed
* Graded and Performed Earthwork Operations
* Completed Mucking, Stone Bridge Lift Installations, and Stream Relocation
* Installed Stormwater Piping and a Drainage Box
* Installed Erosion Controls and Temporary Grassing
* Milled Asphalt off the Bridge Deck
* Completed Water Line Relocation - In Contract
* Completed Preliminary Paving of Re-Aligned Intersection
* 9/17/25 - Held Utility Meeting on Site
* 9/17/25 to 11/26/25 - Utility Relocation window established
* 3/2/26 to 3/4/26 - Crane Delivered
* 3/23/26 - Bridge Subcontractor Mobilized and Began Work
* 3/26/26 to 5/8/26 - Installed Piles
* Approximately 3/23/26 - 4/20/26 - Demolished Existing culvert and Excavated for Bents
* 5/8/26 to 6/23/26 - Forms done, rebar installed, bridge caps poured, and Wing Walls constructed
* Contractor is currently working on installing formwork for the bridge deck pour.

As referenced in previous response, items to be completed are:
* Forming and Pouring the Bridge Deck - working on formwork right now
* Installing the Uniaxial Geogrid at the Approaches (materials placed in soil layers under road beds or bridge approaches to reinforce them)
* Forming and Pouring the Approach Slabs
* Forming and Pouring the Parapet Walls (short walls along edge of bridge)
* Forming and Pouring the Curb and Gutter and Flumes
* Installing the Remaining Storm Drainage Boxes
* Grooving the Deck
* Installing Guardrail
* Making corrections to installed asphalt, and paving the final asphalt surface and driveways
* Installing Pavement Markings
* Installing Rumble Strips
* Installing Signage
* Permanent Stabilization.

I hope this information is helpful. We look forward to the new bridge being completed and opened soon. Thank you.
-SCDOT

Meredith Anderson WRDW Will Rioux WRDW Shawn Cabbagestalk WJBF

07/04/2026
Please be on the look out for missing child Javeayah Harris.
07/02/2026

Please be on the look out for missing child Javeayah Harris.

We were delighted to participate in Midland Valley High School's First Annual Valley Run. Thanks are extended to Casey, ...
05/24/2026

We were delighted to participate in Midland Valley High School's First Annual Valley Run. Thanks are extended to Casey, Shelby, Alisa, and Christian for their participation. We also acknowledge Melvin and Carson for their medical support services during the 24 hour event.

Address

115 School Road
Warrenville, SC
29851

Telephone

803-593-2988

Website

Alerts

Be the first to know and let us send you an email when Midland Valley Fire Department posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organization

Send a message to Midland Valley Fire Department:

Shortcuts

Share

Category