2026 Aggregate Surfacing Project Information ⏩️
*️⃣Aggregate Surfacing for 2026 has begun.
*️⃣The Contractor is currently graveling CR 140.
*️⃣Our Graveling Project will run all summer, with an estimated completion date of August 28th, 2026.
*️⃣See map for roads (marked in red) that will be graveled in 2026. (In no specific order: CR 106, CR 139, CR 140, CR 144, CR 145, CR 151, CR 164). Approximately 25.10 miles in total.
*️⃣All roads will remain open to traffic while graveling is taking place.
‼️Please watch for slow moving equipment & increased semi traffic in these areas. Help to keep work zones safe‼️
Call our office with any questions: 218-631-7636 📞