UPDATED time line:
The original end date was September 18th. INDOT has extended the end date to Friday, October 2nd.
Please be careful in the construction areas.
ROAD REPAIRS
UPDATE:
This construction has been pushed back to start on or about September 01, 2026 and completion is scheduled for September 18th.
Beginning on or around 09/01/2026 construction will start on the Willow Street exit off Highway 41 southbound. This construction will be for widening on both sides of the exit ramp to accommodate larger vehicles and make the turning movement more accessible. On the exit you can expect a shift to either the left or the right of the ramp depending on which side construction is taking place, there will be advanced warning signs on Highway 41 as well. On willow street the right lane will be closed traveling North headed back into Vincennes. This construction will end on or around 09/18/2026 weather pending.