VCPS Construction Progress Report-06.08.2026
New School
The heavy equipment has been busy removing topsoil this past week and is now beginning to take some extra material from Hanna Field that will build up the ground for the new school. Once the ground has been prepped, we are expecting the foundation work to begin around the end of July.
Hanna Field
Right now, the ground at Hanna Field is being excavated to allow for the installation of the stormwater management system for the new school. Once completed, this will connect the existing drainage that was installed with the Dacotah Bank Track in 2019 and the new school. This work is scheduled to be completed by July 24th, thus allowing for the new turf, sponsored by Essentia Health, to be installed by mid-August.
Looking Ahead
Around the middle of July, there will be a temporary road (and walking path) closure on 12th Street between 2nd and 5th Avenue. This will allow contractors to connect into utilities under the street on 12th. We will make every effort to limit the impact and duration of this closure on the neighborhood and community. Please look for more specific details about this closure coming at the beginning of July.
Site Security and Safety
A perimeter fencing has been installed around the construction site in an effort to keep everyone safe, especially our children. Signs have been added along 12th Street to kindly remind drivers and pedestrians to be alert for truck traffic coming and going from the construction site. Please help us to keep everyone safe throughout the project and be alert to the increased traffic around the area.
If you have any questions or concerns about these projects please contact us at the district office at 701.845.0483 ext. 0.