The Door County Highway Department will begin a road reconstruction project on CTH T, from State Highway 42/57 to the Lily Bay Boat Launch. The project will consist of cutting of driveways and intersections, pulverizing existing asphalt, grading and compaction, paving, shouldering, and centerline striping.
The saw cutting of driveways and intersections, along with pulverizing will take place the week of June 1, 2026. Grading and compaction will follow. Paving is scheduled to start the week of June 15, 2026 and will take about two weeks. After a short cure period the road will then be shouldered and centerline stripped.
Every effort will be made to keep access open to traffic as much as possible throughout the construction project. Paving operations may require lane closures, flagmen will be used to control traffic. An oil adhesive will be applied between the two lifts of asphalt so we ask you adhere to flagman and do not driving on the oil surface.
The expected completion date, without the centerline striping, is July 9, 2026. As with any road construction project, the work is controlled by favorable weather. We apologize for any inconvenience that may occur. Please be advised to use caution when traveling around road construction equipment and crews and obey all signage.