๐ง Vine Road Night Work Notice
As part of the Eversource CT Underground Cable Modernization Project, crews will be performing night work on Vine Road to install new underground duct banks beginning Tuesday, September 8 through Tuesday, September 22.
๐ Work hours will be from Monday through Friday, 8:00 PM โ 6:00 AM.
Drivers and residents in the area should expect nighttime construction activity and possible traffic impacts during this period. Please use caution when traveling through the work zone and follow all posted signage.
Thank you for your patience as this important infrastructure work moves forward.
For more information on the project, visit: https://www.eversource.com/residential/about/transmission-distribution/projects/underground-cable-modernization/ucmp-stamford.
A proposed replacement of existing 115-kilovolt (kV) high pressure fluid-filled underground transmission lines with new 115-kV double circuit cross-linked polyethylene (XLPE) transmission lines.