08/05/2026
Heads up from TxDOT! For updates on this project, keep watch on TxDOT's page Texas Department of Transportation or visit their website at My35WacoSouth.com.
I-35 WACO SOUTH | Beginning Friday night, TxDOT and its contractor will begin removal of the South Valley Mills Drive direct connect to northbound I-35 as part of the My35 Waco South Construction Project.
Work will take approximately 24 hours and require closure of:
• All I-35 mainlanes between New Road and 12th Street
• East/westbound crossings at 17th & 18th Streets, Valley Mills Drive, and Irving Lee Street/Primrose Drive
Following the removal, the Irving Lee Street/Primrose Drive underpass will remain closed for an additional 14 days for drainage and utility work, with reopening anticipated on Saturday, Aug. 22.
These closures will allow crews to safely remove the direct connect and begin preparations to construct the new Diverging Diamond Intersection (DDI) planned for the area.
For more information and updates, visit My35WacoSouth.com.