06/02/2026
Streetscape IV's Green Streets project (block from High Street to Maplewood Street) construction will begin in earnest of June 8. Beginning on June 8, Maplewood Street (the lowest section) from Butler Street to Spring Alley which is the road connecting High and Maplewood Streets where the food bank entrance is, will be closed to traffic and remain closed until June 30th. This closure is for the installation of the underground storage tank and "rough" restoration (permanent repairs will occur later in the project). Subsequent phases of this project which include new sidewalk installation, decorative grate installation, curbs, pavement restoration and tree plantings in that section of Butler Street, will begin around June 15th and run through mid to late August. Project is expected to be complete by early September.