06/12/2026
This week, construction work continued for both the Downtown Revitalization and Fort Meigs Road Ditch Projects:
๐ง Downtown Revitalization Project โ The contractor continued electrical improvements at the public restroom facility on East Second Street this week. Crews removed outdated electrical wiring and one of the existing electrical panels in preparation for the installation of new wiring and a new lighting relay panel. Electricians also worked in the attic installing conduit as part of the upgrade project.
In addition, FirstEnergy was onsite to disconnect power to the traffic signal control boxes at the East Second Street and Front Street intersection.
Next week, concrete crews are scheduled to return to the area near Waterford Bank, while electricians will continue work on traffic control box foundations and conduit installation. This work is part of the ongoing preparations for the planned traffic shift during the week of July 6.
๐ง Fort Meigs Road Ditch Reconstruction โ The contractor continued clearing and grading work along the ditch banks this week. To maintain water flow during construction, crews installed a temporary steel plate d**e and set up a pump system to divert water around the section of the ditch where the bottom is being raised.
The new ditch bottom at the drop structure is approximately six feet higher than the existing ditch. Water is pumped from the temporary d**e to the drop structure, which is designed to reduce the speed and energy of the water as it transitions down to the existing ditch elevation.
Next week, the contractor will continue grading work within the ditch. Sheet piling is scheduled to be delivered during the week of June 22, with installation equipment expected to arrive and begin driving the sheet piles during the week of June 29.
Read more about all of Perrysburg's ongoing construction projects by visiting the City's website: https://bit.ly/perrysburgprojects