06/13/2026
Paving Operations (Tuesday, 6/16 through Friday, 6/26)
Please be advised that roadway improvement work is scheduled to begin on Tuesday, June 16th, and continue through Friday, June 26th, weather permitting.
Prior to paving operations, the contractor (Laura Li Industries) will begin construction and upgrades of ADA-compliant curb ramps at various intersections within the project area. Following completion of the ADA ramp work, the contractor will proceed with roadway milling and paving operations on the following streets:
— First Street (Elderwood to Corona)
— Elderwood Avenue (Colonial to First Street)
— Second Street East (Cliff to Ancon)
— River Avenue (Fifth Street to the dead end)
— Third Avenue (Sixth Street to Lincoln)
— Central Avenue (Maple to Linden)
During construction, temporary parking restrictions will be in effect. Please observe all posted signs and allow additional travel time when entering or exiting these areas.
We appreciate your patience and cooperation as we complete these important roadway improvements.
If you have any questions, please contact us at (914) 738-2015 or [email protected].