05/22/2026
About to get rolling. This will address the cold patch areas from this winters construction.
The 2026 Mill and Overlay and Mill Towns State Trail Improvements Project is set to begin on Tuesday, May 26.
The project will fix and extend the life of the road, improve and install sidewalks, pedestrian ramps, and safety features to numerous intersections, and construct a segment of the Mill Towns State Trail. The project is broken into three phases.
Phase 1 is expected to be completed by early July. Phase 1 includes Jefferson Parkway from Maple Street to Spring Creek Road, Prairie Street from Meadowview Drive to Jefferson Parkway and Spring Creek Park Trail. These streets will be open to local traffic only, with detours navigating through traffic around the work area via Superior Drive and Maple Street.
Phase 2 is scheduled to begin early-July and be completed by early August. Phase 2 includes Jefferson Parkway from Wilcox Boulevard East to Maple Street, including the Maple Street and Jefferson Parkway intersection, Maple Street from Jefferson Parkway to Meadowview Drive and Maple Court.
Phase 3 is expected to begin early August and be completed by early September. Phase 3 includes Jefferson Parkway from Wilcox Boulevard East to Division Street (TH 246).
The City of Northfield is committed to being forward-thinking by enhancing the quality of city streets for all Northfield residents. The City of Northfield urges motorists to always drive with caution, slow down in work zones, and never enter a road blocked with barriers or cones.
For more information and to sign up for regular updates, visit the project webpage:
northfieldmn.gov/2026Project
__
El Proyecto de mejora de la ruta estatal “Mill and Overlay and Mill Towns” está previsto que comience el martes 26 de mayo.
El Proyecto permitirá reparar la carretera y prolongar su vida útil, mejorar e instalar aceras, rampas peatonales y elementos de seguridad en numerosos cruces, asà como construir un tramo del Mill Towns State Trail. El proyecto se divide en tres fases.
Se prevĂ© que la fase 1 estĂ© terminada a principios de julio. La fase 1 abarca Jefferson Parkway, desde Maple Street hasta Spring Creek Road; Prairie Street, desde Meadowview Drive hasta Jefferson Parkway; y el sendero de Spring Creek Park. Estas calles estarán abiertas Ăşnicamente al tráfico local, y se habilitarán desvĂos para desviar el tráfico alrededor de la zona de obras a travĂ©s de Superior Drive y Maple Street.
Está previsto que la fase 2 comience a principios de agosto. La fase 2 abarca Jefferson Parkway desde Wilcox Boulevard East hasta Maple Street, incluida la intersección de Maple Street y Jefferson Parkway, asà como Maple Street desde Jefferson Parkway hasta Meadowview Drive y Maple Court.
Se prevé que la fase 3 comience a principios de agosto y finalice a principios de septiembre. La fase 3 abarca el tramo de Jefferson Parkway que va desde Wilcox Boulevard East hasta Division Street (TH 246).
El Ayuntamiento de Northfield se compromete a adoptar una visiĂłn de futuro mejorando la calidad de las calles de la ciudad para todos los habitantes de Northfield. El Ayuntamiento de Northfield insta a los conductores a circular siempre con precauciĂłn, reducir la velocidad en las zonas de obras y no entrar nunca en una vĂa bloqueada con barreras o conos.
Para obtener más información y suscribirse a las actualizaciones periódicas, visite la página web del proyecto:
northfieldmn.gov/2026Project