09/14/2026
The Village has been advised that the contractor for the Village's Water Infrastructure Project will start mobilizing materials & equipment the week of 21 September. Storage for this equipment will be in the gravel pit on Rt. 8 south of the Village. Construction-related activities will begin on Mitchell Dr (between Hill St & West St) the week of 28 September. This will be followed by activities on School & Hill Streets in October and West Street in November. Construction hours will be from 7:30-4:00 PM. Additional construction scheduling will be provided as details become available.