08/17/2026
Natick GIS Presents... South Natick Dam Update, August 17, 2026
Early post this week as your pilot is going on vacation. The weir and apron have been demolished. Work continues on the apron wall (see last image). The project is on time and on budget, with in-water work to be complete by 8/31.
https://www.natickma.gov/1676/Project-Dam-Removal-River-Restoration
Town of Natick, MA