04/17/2026
Latest Update from VTrans on the Route 7 Construction Project (Hourglass)
Contact VTrans with any questions on this project.
Public Information Consultant
Toni Marie Pignatelli
802-267-7717
[email protected]
CONSTRUCTION UPDATES
Construction activities are scheduled to begin on April 20, 2026. ECI will be on site installing approach signage and completing EPSC (Erosion Prevention and Sediment Control) measures.
TRAFFIC UPDATES
Minimal traffic impacts are expected during the week, as most work will occur outside of the roadway. Drivers may notice the presence of blue lights to enhance worker safety.
--------------------------
Updates from VTrans on this project are posted regularly. Community members can sign up at any time to receive these updates directly in their inbox by filling out this form:
https://lp.constantcontactpages.com/sl/MiMzUvY?source_id=a32f23e7-4c17-4ce7-9526-901a67303c7e&source_type=em&c=DVtj8-J1bT_h5wUmL866Zi7Pwq-MAXVxzeDbCMQ1oz_KHkUduXT8tw==
You can also follow this page on Milton's website where updates on this and other VTrans projects are regularly posted: https://miltonvt.gov/CivicAlerts.aspx?AID=261
Project is for improvements to the US Route 2 and US Route 7 intersection and the US Route 2 and Interstate 89 Exit 17 intersections. Project also includes bridge replacement and corresponding roadway improvements.