🚧 Stonefield Reconstruction Project Update 🚧
Despite several days of unfavorable weather, construction continues to make steady progress.
This week, the contractor completed pulverizing operations and continued grading activities throughout the project area. The subcontractor also began adjusting manholes in preparation for future paving operations.
Looking ahead to the week of June 15–19, crews are expected to complete fine grading and finish the remaining manhole adjustments. If weather conditions cooperate, these activities will position the project for paving operations to begin the following week.
Residents should continue to expect construction equipment activity, periodic lane restrictions, increased truck traffic, and temporary impacts to roadway access as work progresses.