Menlo Park Senior Center

Menlo Park Senior Center Visit https://menlopark.org/seniorservices The Menlo Park Senior Center is closed. Services have been relocated to other facilities.

Permanently closed.

The Menlo Park Senior Center is closed as part of the development of a new multigenerational facility including the Onetta Harris Community Center, Belle Haven Youth Center, Belle Haven Pool and branch library. This is part of the development of a new multigenerational facility to incorporate the current Onetta Harris Community Center, Menlo Park Senior Center, Belle Haven Youth Center (child care), Belle Haven Pool and branch library. Learn more at menlopark.org/seniorservices

Menlo Park Community Campus foundation pour set for March 5Level 10 Construction will pour the building foundation for t...
02/19/2022

Menlo Park Community Campus foundation pour set for March 5

Level 10 Construction will pour the building foundation for the city’s new community campus, located at 100 Terminal Ave., on Saturday, March 5, 2022. Completing the building’s foundation is a key project milestone as we work toward the facility’s opening date in 2023.

The City of Menlo Park and Level 10 Construction have carefully planned and coordinated this phase of work.
• To reduce impacts to residents, work will take place 3 a.m. to 4 p.m., Saturday, March 5.
• An exception to the city noise ordinance is needed for work from 3–9 a.m.
• Concrete pumps will setup at 3 a.m., ahead of the first concrete truck arriving at 4 a.m.
• Concrete trucks will travel along the approved truck route (attached).
• We estimate that 2,900 yards of concrete are needed.
• A street sweeper will work during the pour to help keep city streets clean.

Kelly Park will remain open to the public throughout the work. Flaggers stationed at the site will help pedestrians and vehicles safely enter and exit the park.

For this day, we recommend that visitors park on nearby streets and walk to Kelly Park, as on-site parking will be limited.

View the letter and map to be provided to nearby residents on our website at menlopark.org/communitycampus

El 5 de marzo se realizará el vertido de los cimientos del Campus Comunitario de Menlo ParkLevel 10 Construction verterá...
02/19/2022

El 5 de marzo se realizará el vertido de los cimientos del Campus Comunitario de Menlo Park

Level 10 Construction verterá el cemento para los cimientos del nuevo campus comunitario de la ciudad, ubicado en 100 Terminal Ave., el sábado 5 de marzo de 2022. Completar los cimientos del edificio es un hito clave del proyecto mientras trabajamos para la fecha de apertura de las instalaciones en 2023.

La ciudad de Menlo Park y Level 10 Construction han planeado y coordinado cuidadosamente esta fase de trabajo.
• Para reducir el impacto a los residentes, el trabajo se llevará a cabo de 3 a.m. a 4 p.m. el sábado 5 de marzo.
• Se necesita una excepción a la ordenanza de ruido de la ciudad para trabajar de 3 a 9 a.m.
• Las bombas de cemento se instalarán a las 3 a.m., antes de que llegue el primer camión de cemento a las 4 a. m.
• Los camiones de cemento viajarán a lo largo de la ruta aprobada para camiones (adjunto).
• Estimamos que se necesitan 2,900 yardas de cemento.
• Un barrendero trabajará durante el vertido para ayudar a mantener limpias las calles de la ciudad.

Kelly Park permanecerá abierto al público durante todo el trabajo. Los abanderados estacionados en el lugar ayudarán a los peatones y vehículos a entrar y salir del parque de manera segura.

Para este día, recomendamos que los visitantes estacionen en las calles cercanas y caminen hasta Kelly Park, ya que el estacionamiento en el lugar será limitado.

Vea la carta y el mapa que se entregará a los residentes cercanos en nuestro sitio web menlopark.org/communitycampus

As a reminder, senior programs have moved to the Arrillaga Family Recreation Center during construction.
08/10/2021

As a reminder, senior programs have moved to the Arrillaga Family Recreation Center during construction.

Menlo Park Community Campus proceeds with building demolition
August 10, 2021 to October 2021: Demolition of the buildings will begin, which will have noise, vibratory and dust impacts to the surrounding area. Noise will comply with the City of Menlo Park noise ordinance for construction projects and dust will be mitigated by using the appropriate amount of water to spray active work areas. More info at menlopark.org/communitycampus

The Menlo Park Senior Center is closed as part of the development of a new multigenerational facility including the Onet...
06/11/2021

The Menlo Park Senior Center is closed as part of the development of a new multigenerational facility including the Onetta Harris Community Center, Menlo Park Senior Center, Belle Haven Youth Center, Belle Haven Pool and branch library. Visit https://menlopark.org/communitycampus.

Senior services have relocated to the Arrillaga Family Recreation Center and Menlo Park Library. Learn more at menlopark.org/seniorservices

Check out activities and services offered for older adults in Menlo Park.

05/18/2021

Menlo Park Community Campus project moves forward with utility work

Starting Monday, May 24, the construction team will begin utility exploration and excavation throughout the Onetta Harris Community Center parking lot as part of the Menlo Park Community Campus project. The work is expected to last two weeks and public access to Kelly Park and Beechwood School will be maintained.

Learn more: https://www.menlopark.org/Blog.aspx?IID=1742

PARKING AND TRAFFIC ALERT – Menlo Park Community Campus portables deliveryMonday, April 19, at approximately 10:30 a.m.,...
04/17/2021

PARKING AND TRAFFIC ALERT – Menlo Park Community Campus portables delivery

Monday, April 19, at approximately 10:30 a.m., portables will be delivered to the Kelly Park parking lot. These temporary facilities are part of the interim services plan for the Menlo Park Community Campus project (menlopark.org/communitycampus).
The delivery should be completed by Noon, and remaining parking reopened.

To prepare for this delivery, the Kelly Park field parking lot will be closed Sunday evening, April 18. Parking is also restricted in the main parking lot between the Onetta Harris Community Center and Beechwood School, near the campus entrance by Terminal Avenue.

The Senior Center parking lot, between the Onetta Harris Community Center and Kelly Park will remain open for parking Sunday evening and Monday, but may be blocked between 10:30 a.m. and Noon, Monday, April 19, at the trucks pass by.

The delivery route will bring the portables (via semi / tractor-trailer) from Bayfront Expressway, along Chilco Street to Terminal Avenue, down Terminal Avenue to the campus of Onetta Harris Community Center, Menlo Park Senior Center and Kelly Park.

The estimated time for the portables to reach the campus is 10:30 a.m. and remaining parking should be reopened by Noon, Monday, April 19.

10/03/2020

On October 5, 2020, the Planning Commission will hold a study session to review the Menlo Park Community Campus project. The proposal also includes a future request for a use permit for the use and storage of hazardous materials including pool chemicals and diesel fuel for a backup generator. Learn more: https://publicinput.com/Q280853

Menlo Park Community Campus project item at Sept. 15 City Council meeting. On December 16, 2019, Facebook submitted its ...
09/15/2020

Menlo Park Community Campus project item at Sept. 15 City Council meeting. On December 16, 2019, Facebook submitted its proposal for exploring the funding and development of a new multi-generational facility to incorporate the current Onetta Harris Community Center, Menlo Park Senior Center, Belle Haven Youth Center (child care), Belle Haven Pool and branch library.

At the September 15, 2020, City Council special meeting, the City Council will consider the term sheet, conceptual design and project review process of Facebook's offer to rebuild the community facilities located at 100-110 Terminal Ave.

Staff reports and background information available on the city website.

Read more / Leer en español: menlopark.org/communitycampus

August 29, 2020 - This week's features• Stay safe - stay distant - wear a face covering• Child care and after school car...
08/29/2020

August 29, 2020 - This week's features
• Stay safe - stay distant - wear a face covering
• Child care and after school care registration open
• We want your feedback - online suggestion box
• Free virtual community events
Read more / Leer en español: https://www.menlopark.org/CivicSend/ViewMessage/Message/121651

Address

110 Terminal Avenue
Menlo Park, CA
94025

Alerts

Be the first to know and let us send you an email when Menlo Park Senior Center posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organization

Send a message to Menlo Park Senior Center:

Share