09/09/2026
Some updates for Wednesday into Thursday. 
Highway… we will be hot paving the driveway ends on the Woodlawn drain project we did in July. The crew prepared them for tomorrow. Our road tractors are still out road side mowing and the big arm is doing guard rails and back side of ditches.
We completed sweeping the loose stone off of Ritchie, Powell and Toby in preparation for some micro pave. We also have swept Jones, Carey and Candella express for a chip seal.
Our Sanitation crew is a bit behind from having Monday off. It’s steel week so the crew is using Highways help too.
Oneida county DPW will be repaving Fox as soon as they can. Please realize with the late state budget pass it put a lot of municipalities 2 months behind. Pretty much we’re all at the mercy of the weather and when it’s go time. Have a great night! ✌️