Kingsford Water/Sewer Projects Construction Update – 9/11/2026
Resident Update
The City of Kingsford is continuing progress on several water, sewer, storm sewer, concrete, gravel, and paving improvements throughout the community. Below is the latest project
status and anticipated schedule for affected streets.
Current Project Status
• Cass Avenue, Sheridan Street to Ripley Street: Watermain installation is complete. Crews are expected to begin work on water services around the first week of October.
• Cass Avenue, Carpenter Avenue to Kimberly Avenue: Watermain installation is complete. The contractor plans to bore water services into homes beginning this week and continuing through the end of September.
• Hamilton Avenue: Pipe work and concrete work are complete. Concrete sidewalksare expected to be finished next week. Gravel has been placed, and paving is anticipated by the end of next week.
• Ripley Street, from the school to Woodward Avenue: Watermain and storm sewer work are complete. Concrete curbs, sidewalks, and gravel are also complete. Paving is expected to be scheduled for the end of next week.
• Sheridan Street, Hamilton Avenue to Woodward Avenue: Watermain and storm sewer work are complete. Gravel placement is expected next week.
• East Breen Avenue: Final paving is scheduled for the end of next week. Residents are encouraged to use caution near active construction areas and follow posted signage or direction from crews.
Schedules may change due to weather, material
availability, or other field conditions. Thank you for your patience as these important infrastructure improvements continue.