There will be a lot going on in the city this summer. Below is a breakdown of the projects and estimated start dates.
Water tower cleaning and painting. This process started last week and the tower will be drained on the 10th of July. Project should be completed by the end of July.
New water plant project-Should start around August 1st and will take 6 to 9 months to complete.
6th street project-Should start around July 22nd. This includes paving 3rd st, 4th st, and 5th street between 3rd ave and 4th ave. Paving 6th st from Water st. out to Westview school. Sidewalks will be added from 3rd st to Westview school.
Railroad crossing on 6th st. They will shut down the crossing for 3 days to add automatic arms to the crossing for safety reasons. We will update the date when we hear back from the railroad, but it should be in July.
Water street paving. This could happen this fall or early next spring, still working on dates on this one. 1st phase will be from state road 22 to 5th st. This includes paving and new sidewalks. 2nd phase will complete the paving of Water st and also includes new sidewalks.
As you can see, we have several projects lined up this year. There will be road closures, but it will be worth it in the end.
I will update this list if anything changes or we receive any updates.