City of Jasper, Georgia

City of Jasper, Georgia The City of Jasper, the County seat of Pickens County Georgia, was founded in 1857. There were 3,684 residents at the 2010 census.
(2)

Residents enjoy quality living and services including water and sewer.

06/13/2026

See you soon at Perrow Park!

Agenda for the Special Called Council Meeting on Monday, June 15, 2026, at 6:00PM.  The meeting location will be at Chat...
06/12/2026

Agenda for the Special Called Council Meeting on Monday, June 15, 2026, at 6:00PM. The meeting location will be at Chattahoochee Technical College - Appalachian Campus located at 100 Campus Drive, Jasper, GA 30143.

06/11/2026

*๐—š๐—˜๐—™๐—” (๐—š๐—ฒ๐—ผ๐—ฟ๐—ด๐—ถ๐—ฎ ๐—˜๐—ป๐˜ƒ๐—ถ๐—ฟ๐—ผ๐—ป๐—บ๐—ฒ๐—ป๐˜๐—ฎ๐—น ๐—™๐—ถ๐—ป๐—ฎ๐—ป๐—ฐ๐—ฒ ๐—”๐˜‚๐˜๐—ต๐—ผ๐—ฟ๐—ถ๐˜๐˜†) ๐—จ๐˜๐—ถ๐—น๐—ถ๐˜๐˜† ๐—ฃ๐—ฟ๐—ผ๐—ท๐—ฒ๐—ฐ๐˜ ๐—จ๐—ฝ๐—ฑ๐—ฎ๐˜๐—ฒ๐˜€*

๐˜พ๐™ก๐™š๐™–๐™ฃ ๐™’๐™–๐™ฉ๐™š๐™ง ๐™‹๐™ง๐™ค๐™Ÿ๐™š๐™˜๐™ฉ๐™จ - the name is a little misleading, but "clean water" refers to all projects related to sanitary sewer/wastewater.

1. Sanitary Sewer Collection System Rehab - the first project is focused on our North/Northwest Sewer Basin. This area is everything on the west side of 515 from north of Philadelphia Road down to and including the Hospital, and also includes the east side of 515 starting north of Philadelphia Road down to and including the QT Gas Station on Hazel Mosely/Camp Road. Main Street is the dividing line between this basin and the next one to the east. This project involves cleaning & televising the gravity sewer main in Zone 1 of this basin, cleaning & inspecting all sewer manholes, and then fixing the problems identified during televising and inspections. The cleaning & televising work, as well as the manhole inspection work, is complete, and some rehab work that was identified during televising that could not wait was taken care of early on. What remains are the gravity sewer mains that were identified as needing CIPP (cured in place pipe) lining and there are still manholes remaining to be rehabbed. Installing SCADA at our sewer lift stations is also included in this work, and the contractor has these units on order. The original project budget for this work was $1.5M dollars, and the awarded contract to Inliner was a total of $1,630,959.00. Council agreed to use 2026 SPLOST for anything over the $1.5M budget. As it turns out, we are underbudget for this 1st zone, and have released another 59,000 LF of pipe to be cleaned and televised - moving into the next area that needs to be done.

2. Master Sewer Lift Station and upgraded gravity sewer and force main - this project will allow us to decommission two of our oldest, beyond their useful life sewer lift stations; both of which are undersized and by Town Creek. The City owns property on Mineral Springs Rd N and the new station is in the process of being built there. The project budget for this one is $3M dollars - UWS, Inc was the awarded contractor with a low bid of $2,398,719.30. As mentioned at last week's Council meeting, the new gravity main coming to the station and the new force main leaving the station were fully designed to be in the right of way; however field conditions have changed the design a bit and the gravity sewer will be constructed within one of the travel lanes now. The County has approved the right of way use permit for this design change, and in the coming weeks the contractor will start construction of these mains to take advantage of no school traffic.

*Both of the Clean Water projects are critical to identifying I&I (inflow and infiltration) within the collections system - this is groundwater that enters the sanitary sewer collection system, through the manholes, through cracks/breaks in your gravity main, etc. It takes away the available capacity from the treatment plant, as well as throughout the collection system, which can result in overflows, spills, etc. The entire collections system throughout the City needs to be cleaned and televised - this project was our starting point because of the development already approved within this zone.

๐˜ฟ๐™ง๐™ž๐™ฃ๐™ ๐™ž๐™ฃ๐™œ ๐™’๐™–๐™ฉ๐™š๐™ง ๐™‹๐™ง๐™ค๐™Ÿ๐™š๐™˜๐™ฉ๐™จ - these are projects that are specific to potable water, whether it be the treatment plant, within the distribution system, or improving water supply.

1. Water Treatment Plant Rehab - this is not a capacity enhancement project, but rather a much-needed project to redo the electrical components of the plant, replace valves within the plant, and includes replacing the filter underdrains and filter media. The City's budget for this project is $2M dollars, and you may recall hearing at previous Council meetings that the original bids came in significantly higher than our budget - more than 2X our budget. Our Engineer worked with the bidders to reduce the scope of work down to just below $2M dollars, which will allow the electrical upgrades, valve work, and the filter work - all must haves. There is also a contingency amount in that award which will allow us to do some other upgrades to the facility such as a new roof, new security fencing and cameras. Rehab Construction was the low bidder at a bid amount of $1,968,317.30. The electrical work is underway, but the filter work cannot be done during the summer as those are historically our highest demand months. That work will be done during the winter months.

2. Water Distribution System Upgrades - this project has a budget of $1.5M dollars, and we originally planned to use this money to strengthen an interconnect with one of the systems we purchase finished water from AND replace/upgrade the water main in one of the many neighborhoods that has aging, leaking infrastructure (plus didn't have appropriately sized water main to provide fire protection). Both of these projects have been designed, but we cannot do both projects with the amount of money we have available. In previous meetings, you may have heard us mention the Hurricane Helene Resiliency Program, which was introduced by GEFA after Hurricane Helene and is a program designed to build resiliency within your drinking water system and reduce risk. It is 100% a program designed to help communities be more protective of their existing customer base and to provide back up systems to keep the distribution system flowing in case of an emergency. Even though Pickens County was not one of the counties included in this program, we were encouraged by GEFA to apply for a project that would give us the ability to buy additional finished water. We were notified that we were included in the Draft Intended Use Plan sent to EPA for funding, and are simply waiting to hear a final decision on our application. If formally approved, we'll need this money to provide our local match.

*For those of you who have talked about the importance of constructing a reservoir, I don't disagree with you; however, remember that communities that do have reservoirs have larger water bodies available to fill those reservoirs. Long Swamp Creek is the City's permitted surface water withdrawal point to send RAW water to the treatment plant for processing into finished, clean, drinking water. We have a permit that allows us to withdraw up to a maximum amount each day, as long as the creek is flowing at a certain velocity or higher. You may hear this being referred to as "meeting our 7Q10", and that value is different depending on the month we're in. What EPD is really requiring is that the amount we withdraw remains protective of all downstream users - the folks who have withdrawal permits of their own further down the line, as well as the aquatic and biologic life in the creek. Long Swamp Creek is simply not an adequate source of water to fill a reservoir.

Also discussed at the June Council meeting is a project that our on-demand utility contractor is constructing in the Twin Mountain Lakes area - this is replacing old 2" main serving lots of people with new 6" water main that will allow this area to have fire protection. This is another neighborhood where we've had numerous leaks and problems. This is a $500,000.00 project (approximately) and we're using a combination of 2020 SPLOST dollars and 2026 SPLOST dollars. This should be ready for pressure testing, chlorination and bac-t testing very soon and then we'll certify it through EPD and get everyone tied over to the new main.

Thanks for reading.

๐—ช๐—ต๐—ฎ๐˜ ๐—ฎ๐—ฟ๐—ฒ ๐—ฌ๐—ข๐—จ ๐—ฑ๐—ผ๐—ถ๐—ป๐—ด ๐˜๐—ต๐—ถ๐˜€ ๐—ฆ๐—ฎ๐˜๐˜‚๐—ฟ๐—ฑ๐—ฎ๐˜†, ๐—๐˜‚๐—ป๐—ฒ ๐Ÿญ๐Ÿฏ๐˜๐—ต?Join us for the Grand Opening & celebration of Dr. Perrow's contributions to...
06/10/2026

๐—ช๐—ต๐—ฎ๐˜ ๐—ฎ๐—ฟ๐—ฒ ๐—ฌ๐—ข๐—จ ๐—ฑ๐—ผ๐—ถ๐—ป๐—ด ๐˜๐—ต๐—ถ๐˜€ ๐—ฆ๐—ฎ๐˜๐˜‚๐—ฟ๐—ฑ๐—ฎ๐˜†, ๐—๐˜‚๐—ป๐—ฒ ๐Ÿญ๐Ÿฏ๐˜๐—ต?

Join us for the Grand Opening & celebration of Dr. Perrow's contributions to our community at Perrow Park this Saturday, June 13th at 2:00PM, and stay for Jasper Downtown Live with Canon Tyler and Fly Betty Band starting at 5:00PM!!

06/07/2026

June 7, 2026 Heavy Rain Flash Flooding Possible. Pickens County Fire and Rescue Pickens County GA Government City of Jasper Police Department - Georgia Jasper Fire Department Jasper, GA News City of Jasper, Georgia KnowPickens Bent Tree Safety & Emergency Management Big Canoe Events and Happenings Big Canoe Volunteer Fire Department Robby Westbrook

06/06/2026

THANK YOU Downtown Jasper GA, the Pickens County Chamber of Commerce and Visitor Center and Visit Pickens, GA for a great video on Perrow Park! We are so excited for everyone to join us next Saturday, June 13th at 2:00p for the Ribbon Cutting and celebration of Dr. Perrowโ€™s contributions to our community, as well as for Jasper Downtown Live at 5:00pm!

See you soon!

UPDATE 8:35AM - Cove Rd is OPENCove Road is currently CLOSED between Burnt Mountain Road and Still Hollow Drive due to a...
06/04/2026

UPDATE 8:35AM - Cove Rd is OPEN

Cove Road is currently CLOSED between Burnt Mountain Road and Still Hollow Drive due to an extremely low tractor trailer that is having to be backed up Cove Road to the 3 way intersection to turn around as they cannot navigate Cove Road and the S curves. The City of Jasper Police Department - Georgia anticipates the road should be reopened by 9AM at the latest.

UPDATE 2:00pm - road is OPEN!!๐Ÿšง๐—•๐—ถ๐—น๐—น ๐—ช๐—ถ๐—ด๐—ถ๐—ป๐—ด๐˜๐—ผ๐—ป ๐—ฃ๐—ฎ๐—ฟ๐—ธ๐˜„๐—ฎ๐˜† ๐—ฅ๐—ผ๐—ฎ๐—ฑ ๐—–๐—น๐—ผ๐˜€๐˜‚๐—ฟ๐—ฒ - ๐—ง๐—ต๐˜‚๐—ฟ๐˜€๐—ฑ๐—ฎ๐˜†, ๐—๐˜‚๐—ป๐—ฒ ๐Ÿฐ๐˜๐—ต ๐˜€๐˜๐—ฎ๐—ฟ๐˜๐—ถ๐—ป๐—ด ๐—ฎ๐˜ ๐Ÿณ:๐Ÿฌ๐Ÿฌ๐—”๐— ๐ŸšงThe City will...
06/03/2026

UPDATE 2:00pm - road is OPEN!!

๐Ÿšง๐—•๐—ถ๐—น๐—น ๐—ช๐—ถ๐—ด๐—ถ๐—ป๐—ด๐˜๐—ผ๐—ป ๐—ฃ๐—ฎ๐—ฟ๐—ธ๐˜„๐—ฎ๐˜† ๐—ฅ๐—ผ๐—ฎ๐—ฑ ๐—–๐—น๐—ผ๐˜€๐˜‚๐—ฟ๐—ฒ - ๐—ง๐—ต๐˜‚๐—ฟ๐˜€๐—ฑ๐—ฎ๐˜†, ๐—๐˜‚๐—ป๐—ฒ ๐Ÿฐ๐˜๐—ต ๐˜€๐˜๐—ฎ๐—ฟ๐˜๐—ถ๐—ป๐—ด ๐—ฎ๐˜ ๐Ÿณ:๐Ÿฌ๐Ÿฌ๐—”๐— ๐Ÿšง

The City will start roadway repairs on Bill Wigington Parkway Thursday morning at 7:00AM - this first area of repair is between the shopping center entrance to Home Depot and the intersection with Highway 515.

You have likely noticed (and felt) a rough area as you approach the dedicated northbound left hand turn lanes from Bill Wigington Pkwy onto 515 where it looks like the asphalt has melted and been shoved over a large area. This shopping center does have significant large truck travel due to deliveries to Home Depot, Kroger, and the various restaurants in the center, and this travel lane needs to be corrected. We'll start digging out the area at 7:00AM tomorrow and hope to have the roadway re-opened by 3:00PM-ish.

*๐™‹๐™‡๐™€๐˜ผ๐™Ž๐™€ ๐™๐™Ž๐™€ ๐™๐™ƒ๐™€ ๐™€๐™‰๐™๐™๐˜ผ๐™‰๐˜พ๐™€ ๐™„๐™‰๐™๐™Š ๐™๐™ƒ๐™€ ๐™Ž๐™ƒ๐™Š๐™‹๐™‹๐™„๐™‰๐™‚ ๐˜พ๐™€๐™‰๐™๐™€๐™ ๐™๐™๐™Š๐™ˆ ๐˜พ๐˜ผ๐™ˆ๐™‹ ๐™๐™Š๐˜ผ๐˜ฟ
๐˜ฟ๐™๐™๐™„๐™‰๐™‚ ๐™๐™ƒ๐™„๐™Ž ๐™’๐™Š๐™๐™†*

This work is being funded through the City's allotment of LMIG funding - this is provided by GDOT annually, and can be used on roadways, sidewalks, engineering studies, utility work, etc. We plan to take advantage of no school traffic during the summer and will be working on 2 additional areas that have very similar issues in the coming weeks - Philadelphia Road as you approach Talking Rock Road, and Pioneer Industrial Blvd as you approach Gennett Drive. Once we have dates for these areas, we'll let you know.

Jasper Fire Department
City of Jasper Police Department - Georgia
Pickens County Georgia Sheriff's Office
Pickens County Fire and Rescue
Pickens County GA E9-1-1
Pickens Emergency Management Homeland Security Agency
Pickens Progress
KnowPickens
Amicalola EMC
Georgia Power

Recap from last night's City Council meeting - see you at the Work Session on Thursday, June 25, 2026!
06/02/2026

Recap from last night's City Council meeting - see you at the Work Session on Thursday, June 25, 2026!

Address

Jasper, GA
30143

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm

Telephone

+17066929100

Alerts

Be the first to know and let us send you an email when City of Jasper, Georgia posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share