The General Authority of the City of Franklin MH-A-108 Sewer Project tentative schedule for the week of 9/14/2026:
Contract S-1 (Bison Construction, Inc.)
Continue paving on Grant
Then moving to intersection of Grant/13th for waterline prep (late/next week)
Traffic impact:
Grant: 600 to 800 block / Work area with flaggers (paving)
Grant: 100 block / Work area with flaggers (prep)
Contract S-2 (Mortimer’s Excavating, Inc.)
Crew to begin pipe bursting on 14th
Traffic impact:
14th: Liberty – Franklin / Road closures & "No Parking" restrictions
Otter: 13th – 15th / Road closures & "No Parking" restrictions
Elk: 14th – 15th / Road closures & "No Parking" restrictions
Open to business and local traffic; school buses will be permitted to turn onto 14th & onto Elk