The General Authority of the City of Franklin MH-A-108 Sewer Project tentative schedule for the week of 6/15/2026:
Contract S-1 (Bison Construction, Inc.)
Continue lateral excavation on Grant between Missouri/Pine
2nd Crew excavating on Pacific then moving to Pine/Norman
SES continue work on fold and form areas (13th)
Traffic impact:
Grant: 400 – 500 block / Work area with flaggers
Pacific: 600 block / Work area with flaggers
13th / Work area with lane shift (SES)
Contract S-2 (Mortimer’s Excavating, Inc.)
Continue mainline/lateral excavation on Otter between 12th/ West Park
Guyer Brothers installing fold & form on 6/17-6/18
14th between Liberty/Buffalo then moving to Pearl near 12th
Protech paving above 15th on Buffalo, Chestnut, Brownsylvania, Plummer (weather dependent)
Eldon Durstien restoring concrete in various areas (Franklin, Otter, Elk, Liberty)
Traffic impact:
Otter: 12th - West Park / Road closure & "No Parking" restrictions
14th: Otter – Elk then Pearl: intersection near 12th / Road closures (Guyer)
Buffalo, Chestnut, Brownsylvania, Plummer / Road closures & "No Parking" restrictions (Protech)
Franklin, Otter, Elk, Liberty / Road closures & "No Parking" restrictions (Eldon Durstien)