07/29/2025
Watermain, Sidewalk, & Road Construction Ahead
Watermain Work:
Westshire Ct., Westnedge Ave. (Netherfield to Springfield) and cul-de-sac south of Westshire to north of Shadowood, Pemberley Ave., Springfield St., Foxcroft Ave. (west of Westshire - cul-de-sac portion) and Lantern Ct.
14-week long project, July 28 - Oct. 31, 2025. The page for construction status updates for this project can be found here: https://www.preinnewhof.com/construction_projects/westgate-wm-2025/
For questions regarding watermain work, please call Plainfield Charter Township
Road Work:
Alpine Church St. from Alpine Ave. to Cordes Ave. Construction August 18 - October 11, 2025
Alpine Ave. from M-37 north to 10 Mile Rd. crush and shape roadway followed by new asphalt. Construction August 11 - 29, 2025
6 Mile Rd. from Kenowa Ave. to Fruit Ridge Ave. crush and shape roadway followed by new asphalt. Roadwork Sept. 29-Oct. 19, 2025.
Sidewalk installation:
East side Fruit Ridge Ave. from Boyne Blvd. to 4 Mile Rd: August 6, 2025