08/21/2026
🏠 Construction Update! 🔨
There’s a lot happening across our Habitat jobsites as several homes move closer to completion—and we’re already preparing for what’s ahead!
🔹 1996 Blythe – Drywall is going up, siding has started on the gable and back of the home, and the cornice is complete. We’re also preparing for the back slab and working toward water and electrical hookups.
🔹 1998 Blythe – Drywall hanging is complete and finishing work is beginning! J-mold installation for the siding is underway, utility hookups have been requested, and preparations are being made for the back slab.
🔹 122 Southgate – Mechanical, electrical, and plumbing rough-ins are complete and moving into inspections. Insulation and drywall are coming up next, along with work on the retaining wall and preparations for electrical power.
🔹 127 & 135 Southgate – After an unexpected delay with the roof trusses, they are officially back in production! We’re working to get construction schedules back on track so we can keep these homes moving forward.
🔹 Looking ahead at Southgate – Lot clearing has begun for three more homes planned for next year! 🌳➡️🏠
Every sheet of drywall, piece of siding, inspection, and cleared lot represents another step toward affordable homeownership for families in our community. We’re grateful for the volunteers, partners, donors, and construction team who help keep us building! 💙💚