07/19/2026
The FRICO Berm project is set to resume on Monday, July 20, 2026. The project was initiated in 2023 after seepage was observed on the earthen berm (our Lake Loop trail). FRICO worked on the project in 2023 and 2024, from the northeast corner of the dam to the Nature Center pedestrian bridge. In 2025, FRICO had more pressing projects to complete and directed all their resources towards them. This year and next year, they will be returning to Barr Lake to complete their project. The project involves widening the surface of the berm to 23 feet across, creating a 2:1 slope, and removing all woody vegetation within 10 feet from the TOE of the slope (i.e. furthest point the slope extends).
FRICO (Farmers Reservoir and Irrigation Company) owns Barr Lake and the berm - CPW holds a long term recreation management lease on these areas. FRICO is required by Colorado dam safety to stabilize the berm and protect the long-term integrity of the water delivery system. As we’ve done throughout this project, we will continue to work closely with FRICO to minimize impacts wherever possible while allowing this critical infrastructure project to move forward.
Here is a timeline:
* ��Week of July 20: FRICO crews will remove several trees near the Niedrach entrance. During this time, there will be no public trail access from the Nature Center via the pedestrian bridge. The Lake loop trail will be closed from Pioneer cutoff trail to the boardwalk gazebo.
* ��Following week through the end of the year: Crews will move south into the refuge and continue toward the bifurcation structure. We have worked with FRICO to identify the nesting barn owls, and they will adjust their work sequence to minimize disturbance.
* ��Construction will occur Monday through Friday only. Trails will reopen on weekends.
* ��The BCR bird banding station will open in late August and FRICO will adjust operations to avoidinterference with banding operations.