Beach renourishment has begun at Coquina- check out the link for info 🏝️
Dredging of the Coquina Beach restoration project started this week to restore nearly a mile of Coquina Beach with 63,450 cubic yards of sand lost to Hurricane Idalia.
The project, which is federally funded through FEMA at a 75% cost share, with the balance split evenly between the Florida Department of Environmental Protection (FDEP) and Manatee County, is anticipated to be completed in November and will have a secondary benefit of improving navigation through the pass.
Work areas will be marked with temporary construction fencing and will move along the beach as work progresses. Some beach access points may be temporarily closed near active construction areas. The south end of Coquina will be closed for dredging and construction equipment.
Every effort will be made to keep beach access available whenever possible. Work will take place 24 hours a day, 7 days a week, in order to complete the project in the timeliest manner.
Project updates will be posted at https://coquina-nourishment-2026.coastalprotectioneng.com/.