09/04/2026
please remember that this lengthy project is scheduled to begin next week! If you regularly drive Cumberland Street or Harlow Street (and surrounding streets) please be mindful of road closures that are planned. Have alternate routes mapped out to minimize travel delays. Thank you for your understanding as this important infrastructure project gets underway.
A major infrastructure project along Cumberland Street is scheduled to soon begin and will require the closure of Cumberland and, for a shorter period, Harlow Street, too.
The City’s Engineering Department in conjunction with the Bangor Water District will launch the $2.8 million project in early September to replace sewer, lay new storm drain and new water pipe. The complete reconstruction of Cumberland, including pavement and sidewalks, is part of the project.
The project is scheduled to begin by Sept. 8 and for those initial three to five weeks Harlow Street at the intersection with Cumberland will be closed. Motorists on Harlow traveling toward Downtown will be rerouted onto Kenduskeag Avenue, while drivers leaving Downtown will be redirected onto streets like Center and Spring.
The subsequent closing of Cumberland will last into early December.
The work to separate sewer and storm drains is part of the City’s ongoing consent decree commitment with the federal Environmental Protection Agency regarding combined sewer overflows.
Follow this link for more details on the work: https://www.bangormaine.gov/m/newsflash/home/detail/404