09/11/2026
🚨 Centennial Park Update 🚨
Work continues to progress at Centennial Park! Playground demolition is mostly complete, with work expected to resume soon and equipment installation will begin in the coming weeks.
The new baseball field fence and net posts have been installed, stone subbase work is underway for the new asphalt path and concrete surrounding the baseball fields and preparation has begun for the new shelter.
Concrete work has begun and will largely be completed next week weather permitting. Work on the boardwalk is planned for later this fall. Stay tuned for more updates on this exciting project!