06/19/2026
Upcoming work!
‼️Phase I
Monday, June 22 – Saturday, June 27(As Needed)
Daily, 9 a.m. – 4 p.m.
Nightly, 9 p.m. – 6 a.m.
▪️I-10 east and westbound between Vinton and Resler alternate lane closures
▪️North and South Desert between Vinton and Resler alternate lane closures
▪️Entrance ramp, exit ramp, and U-turn, east and westbound between Vinton and Resler alternate lane closures
Crews will be working on punch list items.
‼️Phase II
Monday, June 22 - Saturday, June 27 (As Needed)
Daily, 9 a.m. – 4 p.m.
Nightly, 9 p.m. – 6 a.m.
▪️I-10 east and westbound between Anthony and Mesa alternate lane closures
▪️North and South Desert between Anthony and Mesa alternate lane closures
▪️Crews will be conducting concrete paving, as well as paving trucks will be exiting the work area, crossing from median to I-10.
Monday, June 22- Saturday, June 27 (As Needed)
9 a.m. – 4 p.m.
▪️I-10 east and westbound Bypass lanes between Mesa and Redd full closure
Crews will be completing construction on ornamental fences and landscaping at Thorn.
▪️I-10 westbound exit Ramp 10 (Redd) full closure
Crews will be working on striping repairs.
Tuesday, June 16
11:30 p.m. – 3 a.m. (Night)
▪️South Desert between Antonio Street and Valley Chile full closure
Crews will be re-setting concrete barrier at Valley Chile’s deceleration right lane.