09/04/2026
2026 Street Improvement Project - BRECKENRIDGE-UPDATE
Residents in the Breckenridge area are advised that the City's 2026 Street Improvement Project will include milling and repaving on Breckenridge from #124 to Tollgate, as well as Connie Lane, East and West Boesch, and Horizon Hill Court.
As some residents are aware, storm drain replacement began this past week as a part of our 2026 street plan. Storm work should conclude next week and Riegler crews will begin curb, gutter and apron tear out. This work is scheduled to start on Tuesday 9/8.
As noted below, our contractor, Riegler, will notify residents that will be affected by the first round of improvements.
What residents should expect:
• Contractor crews will contact affected homeowners in advance to coordinate curb and driveway apron replacement. This work may temporarily affect access to driveways for several days.
• Street parking may need to shift from one side of the street to the other as construction progresses. The City will work with the contractor and residents to help coordinate parking as needed.
• A concrete repair on Breckenridge at KY 10 will require a one- to two-day, one-lane road closure. Advance notice will be provided when the closure is scheduled. During this work, motorists will need to use alternate routes.
We appreciate everyone's patience and cooperation while this important street improvement work is completed.
If you have questions about the project, please contact the Alexandria PW Superintendent Mike Hoerlein at 859-635-4125.