25/09/2024
FYI/
๐๐๐๐ ๐๐๐๐๐ ๐๐๐๐๐๐๐๐๐๐๐๐
โ
๐๐ฎ๐๐ฌ๐ญ๐๐ญ๐ข๐จ๐ง: STA. MISERICORDIA FEEDERS 1 AND 2
๐๐๐ญ๐: September 27, 2024 (Friday)
๐๐๐๐: 6:00 AM to 6:00 PM
๐๐๐๐ฌ๐จ๐ง:
- Load Shifting of Daraga - Sorsogon 69kV Line from Daraga 100 MVA Mobile Power Transformer to Daraga 100 MVA T03
- Oil leak correction at Sto. Domingo 10 MVA T01 Transformer top main tank
------------------------------------
โ
๐๐๐๐๐ ๐๐๐๐๐๐๐๐ ๐๐๐๐๐๐๐๐๐๐: ๐๐๐. ๐๐๐๐๐๐๐๐๐๐๐๐ ๐
๐๐๐๐๐ ๐
โ- Massive Right of Way Line Clearing Activity at Calayucay Line Section SDA onward.
๐๐
๐
๐๐๐๐๐ ๐๐๐๐๐/๐๐๐๐๐: (8:00 AM - 5:00 PM)
๐๐๐. ๐๐๐๐๐๐๐
- Brgys. Calayucay, Salvacion, Buhatan, Alimsog
๐๐๐๐๐๐๐
- Brgys. Tambongon (Tambilagao), Bariw, Nahapunan, Sula, Mapulang Daga, Damacan, Misibis, Mataas, Namantao, Cagbulacao, Manaet, Cagraray, Cawayan, Tanagan, Cabasan, Pigcobohan, Tambilagao, Napao, Vinisitahan - Napao Island, Buang, Uson, San Pablo, Langaton, Busdac (San Jose), Namanday
๐๐๐๐๐๐๐๐๐
- Brgys. Salvacion, San Antonio Santicon (Poblacion), San Antonio Sulong
๐๐๐๐๐๐
- Brgys. Agnas (San Miguel Island), Hacienda (San Miguel Island), Rawis (San Miguel Island), Sagurong (San Miguel Island), Visita (San Miguel Island)
All works may be finished ahead of time and power may be restored earlier than scheduled.
Please consider our lines always energized