SH6 UPPER BULLER GORGE, TASMAN – BRIDGE STRENGTHENING
UPDATE 10 JUNE
Plan ahead for ongoing works to strengthen the O’Sullivans Bridge, occasional STOP/GOs will be in place until 3 July as required.
From Monday 6 July to Friday 31 July, STOP/GOs will be in place weekdays between 7:30am-5:30pm, DELAYS of up to 10 minutes are expected.
A 30km/h temporary speed limit will be in place for the duration of the work.
Project engineers have adjusted the design and simplified the construction approach. It means the series of 30-minute planned closures for the bridge, scheduled daily from 15 to 26 June are no longer needed.
Read more here: https://nzta.govt.nz/media-releases/update-closures-no-longer-required-for-state-highway-6-osullivans-bridge-strengthening
Updated NZTA post: https://www.facebook.com/share/p/1BH1VZZ6fg/
SH6 UPPER BULLER GORGE, TASMAN – BRIDGE STRENGTHENING
Plan ahead for various works to strengthen the O’Sullivans Bridge, below is the work schedule:
• STOP/GO’s from Monday 25 to Friday 29 May, 7:30am-5:30pm
• STOP/GO’s from Tuesday 2 to Friday 12 June, 7:30am-5:30pm
• STOP/GO’s from Monday 15 to Friday 26 June, 7:30am-9am & 3:30pm-5:30pm
• 30-minute CLOSURES between 9am-3:30pm on the hour from Monday 15 to Friday 26 June
• STOP/GO’s from Monday 29 June to Friday 3 July, 7:30am-5:30pm
Crews will be working only during the weekdays. Road users are to expect DELAYS of 10-15 minutes when stop/go traffic management is in place.
Full schedule and other details available in our media release here: nzta.govt.nz/closures-required-for-state-highway-6-osullivans-bridge-strengthening