20/05/2026
Another busy and productive day across the site today, with a wide range of works completed by the team.
Floors in areas of the Discovery Ride were freshly repainted, lifting both appearance and durability, while Shipleys was on site fine-tuning key elements to keep everything running smoothly.
Up at the summit, the toilets received a full deep clean, and work continued on the cableway emergency brake systems to support ongoing safety and reliability. Installation of the new air conditioning system also progressed, with crews advancing works within the roof space.
In the café, counters were tidied and finished with aluminium edge strips, alongside the installation of two new splashbacks and a new CommBox. Externally, updated safety signage has been installed to improve clarity for guests.
Additional works included painting of barriers, touch-ups to warning lines at the base station, and general site clean-up to keep everything looking sharp.
Great effort from everyone involved to keep progress moving across multiple areas