22/07/2022
Shutdown of 33kV Bus I, II & III will be required at 132kV Sishugram GSS, AEGCL, North Guwahati-31 on 23/07/22 from 05:00hrs to 09:00hrs for er****on and stringing of bus for commissioning works of new 132/33kV 50MVA Transformer. During the shutdown period there will be no power at all 33kV feeders emanating from Sishugram GSS. Approx 50MW load will be affected.
During this period there will no power under entire Sualkuchi Electrical subdivision. Inconvenience caused is deeply regretted.