Milford-on-Sea Seawall Coastal Maintenance – Phase 2 – June/July 2026
Phase 2 will commence in the week commencing Monday 8 June, with welfare facilities, fencing, a 35 tonne machine and smaller items of plant delivered ahead of the arrival of a large 130 tonne excavator and assembly crane in the week commencing Monday 15 June. General working hours will be between 0700 and 1900 with an anticipated duration of around six weeks.
As this is a large machine, several lorries will be required for delivery, after which the crane will assemble the excavator over two days. To facilitate this operation, a portion of the car park at the eastern end will be temporarily closed. Appropriate signage will be in place to safely re-route vehicles and pedestrians, particularly those moving between the promenade and Hurst Road. All movements will be carefully overseen by traffic marshals to ensure safety.
Upon completion, demobilisation will include the excavator being disassembled within the car park over a further two days before being removed from site.
The large 130 tonne machine is being used due to its very long reach, which enables the placement of large rock armour at a distance from the seawall, avoiding the need to access the beach - otherwise a particularly challenging aspect of the works at this site. This will allow rock (including rock currently held in the stockpile) to be placed to form the permanent revetment repair, providing improved protection to the seawall.
General working hours will be between 07:00 and 19:00, with an anticipated duration of around six weeks. To make best use of suitable weather and tidal working windows, it may be necessary for the contractor to work early mornings, late evenings, or weekends. The aim is to minimise disruption and noise wherever possible.
Further details can be found on New Forest District Council’s dedicated web pages.
https://www.newforest.gov.uk/article/1695/Milford-on-Sea-Seawall-Coastal-Maintenance-Phase-1-winter-2025