Royal Parade Update from North Yorkshire Council
Project: Royal Parade, Filey
Date: 04/09/2026
Progress
Demolition Approved: The demolition application was submitted separately and in advance of any
full redevelopment proposal as a precautionary measure, this was approved at Area Committee on
20th August 2026. As the project moves into the autumn and winter months, there is concern that
adverse weather conditions could contribute to further ground movement. Securing the necessary
approvals in advance allows the Council to respond quickly should the building present an
immediate safety risk in the future.
Any decision to undertake partial or full demolition will be dependent upon the building's ongoing
structural condition and the findings of further assessments. The building is currently supported
internally by temporary acrow props to maintain stability and the site remains securely fenced to
ensure public safety. Colleagues from maintenance will be visiting site in the coming week to assess
the hoarding around the structure to assess its continued suitability and any enhancements
required.
The adjacent kiosks remain open and operational. Structural surveys and ongoing site inspections
have confirmed that these units remain stable and safe for continued occupation.
Wider Project Work
• The Council are finalising the review of development options for the site.
• Officers are working closely with Yorkshire Water to ensure that proposals for the site
address the longstanding issues associated with the existing pumping station and drainage.
• The Council remains committed to delivering a long-term solution for the site as soon as
reasonably practicable. However, sufficient time is being taken to ensure that any
replacement scheme is fit for purpose and capable of meeting the needs of residents,
businesses, visitors and other stakeholders.
• As part of the options appraisal process, careful consideration is being given to the site's
unique challenges and opportunities, including its exposed coastal location and vulnerability
to severe weather and storm events.
• Any future development will need to provide a resilient and sustainable solution capable of
withstanding the demanding coastal environment over the long term.
• Consideration is also being given to construction methods and material choices that may
support a more efficient delivery programme. Modern Methods of Construction (MMC),
including prefabricated or modular elements, may offer opportunities to reduce on-site construction periods, minimise disruption, and provide greater certainty around programme
delivery.
• Any proposed construction approach will need to be balanced against durability
requirements, long-term maintenance considerations, conservation area requirements, and
the need to ensure that any new development is sympathetic to its prominent seafront
location.
• Given the significance of the site, any replacement building will be expected to utilise highquality materials and an architectural approach that complements the character and
appearance of the surrounding area whilst providing a practical, robust and cost-effective
solution.
• Once the options appraisal process has been completed and a preferred option identified,
the Council will be in a position to consider funding requirements and develop an indicative
programme for delivery.
Stakeholder Engagement
• Members and stakeholders will continue to be kept informed as the project progresses.
• Once the options appraisal process has been completed and a preferred option identified,
the Council will engage with stakeholders to present the solution and respond to queries.
• Options for provision of accommodation for the National Coastal Institute are also being
assessed as part of the wider delivery of the site to assist with the continued delivery and
location of this service.