07/09/2026

Royal Parade Update from North Yorkshire Council
Project: Royal Parade, Filey

Date: 04/09/2026

Progress
Demolition Approved: The demolition application was submitted separately and in advance of any
full redevelopment proposal as a precautionary measure, this was approved at Area Committee on
20th August 2026. As the project moves into the autumn and winter months, there is concern that
adverse weather conditions could contribute to further ground movement. Securing the necessary
approvals in advance allows the Council to respond quickly should the building present an
immediate safety risk in the future.
Any decision to undertake partial or full demolition will be dependent upon the building's ongoing
structural condition and the findings of further assessments. The building is currently supported
internally by temporary acrow props to maintain stability and the site remains securely fenced to
ensure public safety. Colleagues from maintenance will be visiting site in the coming week to assess
the hoarding around the structure to assess its continued suitability and any enhancements
required.
The adjacent kiosks remain open and operational. Structural surveys and ongoing site inspections
have confirmed that these units remain stable and safe for continued occupation.

Wider Project Work
• The Council are finalising the review of development options for the site.
• Officers are working closely with Yorkshire Water to ensure that proposals for the site
address the longstanding issues associated with the existing pumping station and drainage.
• The Council remains committed to delivering a long-term solution for the site as soon as
reasonably practicable. However, sufficient time is being taken to ensure that any
replacement scheme is fit for purpose and capable of meeting the needs of residents,
businesses, visitors and other stakeholders.
• As part of the options appraisal process, careful consideration is being given to the site's
unique challenges and opportunities, including its exposed coastal location and vulnerability
to severe weather and storm events.
• Any future development will need to provide a resilient and sustainable solution capable of
withstanding the demanding coastal environment over the long term.
• Consideration is also being given to construction methods and material choices that may
support a more efficient delivery programme. Modern Methods of Construction (MMC),
including prefabricated or modular elements, may offer opportunities to reduce on-site construction periods, minimise disruption, and provide greater certainty around programme
delivery.
• Any proposed construction approach will need to be balanced against durability
requirements, long-term maintenance considerations, conservation area requirements, and
the need to ensure that any new development is sympathetic to its prominent seafront
location.
• Given the significance of the site, any replacement building will be expected to utilise highquality materials and an architectural approach that complements the character and
appearance of the surrounding area whilst providing a practical, robust and cost-effective
solution.
• Once the options appraisal process has been completed and a preferred option identified,
the Council will be in a position to consider funding requirements and develop an indicative
programme for delivery.
Stakeholder Engagement
• Members and stakeholders will continue to be kept informed as the project progresses.
• Once the options appraisal process has been completed and a preferred option identified,
the Council will engage with stakeholders to present the solution and respond to queries.
• Options for provision of accommodation for the National Coastal Institute are also being
assessed as part of the wider delivery of the site to assist with the continued delivery and
location of this service.

This Sunday brings the last of our Summer Bandstand Concerts in Crescent Gardens.The West Yorkshire Brass Band will be p...
03/09/2026

This Sunday brings the last of our Summer Bandstand Concerts in Crescent Gardens.

The West Yorkshire Brass Band will be playing from 2pm to 4pm.
Deckchairs available.

Make the most of the wonderful September weather, while it lasts!

01/09/2026

Information for Road Users from NORTH YORKSHIRE COUNCIL

Location: The Croft, Filey (outside 39-43) 3rd September 2026
Traffic management and some carriageway incursion

Work descriptions

Description
Patching takes place to repair the road surface, it involves removing a part of the surface around a pothole or defective surface course and placing a new patch of road surface. This is a cost-effective method to repair damage when a small area is affected. Patching works can be carried out in individual locations along a section of road, depending on the road condition .

https://one.network/?GB152129423

Information for Residents

Contact North Yorkshire Council If you have an enquiry in respect of these essential highway works please contact us on 0300 131 2 131.
Our opening hours Mon and Tues 9am to 5pm; Wed 9.30am to 5pm; Thurs 9am to 5pm and Fri 9am to 4pm

Congratulations to POC Wilson and LC Eblet😀
01/09/2026

Congratulations to POC Wilson and LC Eblet😀

01/09/2026

OUR MOST RECENT UPDATE FROM NORTH YORKSHIRE COUNCIL ON THE WORK AT ROYAL PARADE.

ANOTHER UPDATE WILL BE DUE SHORTLY.

Project Update - Royal Parade, Filey
Project Number: 25011
Date: 21/08/2026

Progress
Planning permission has been granted (20/08/26) by Area Committee for the demolition and clearance of the Royal Parade building.
This includes the toilet block, Yorkshire Water pumping
station, café and kiosks. Immediate demolition will only occur if further movement of the structure takes place and it is decided that further intervention is not appropriate and there is a risk to the
public.
The application was submitted ahead of a full scheme application as risks were identified relating to oncoming seasons and poor weather, the approval allows us to action demolition if required.

Heras fencing and banners have been installed around the site to improve its appearance.
North Yorkshire Council will continue to inspect and maintain the fencing as needed.

There have been no major incidents with the temporary toilet provision on the site, all minor issues
are being addressed within acceptable timescales.

Wider Project Work
• RIBA Stage 1/Feasibility (the preparation and brief stage) reports have been received and are
being reviewed with clarifications and queries issued to Consultant team.
• Based on Stage 1 information, work is continuing to explore options for the new
development. Consideration is being given to the needs of current and future users of the site and location. The Options are being actively developed internally by officers. We hope to provide updates in the next month.
Temporary Toilets
• There are now 13 toilets available, including one accessible toilet. These have been installed
under permitted development rights.

27/08/2026

⚠️ Yellow Weather Warning in Place

As heavy rain and thunderstorms are forecast for today, please take extra care if you're travelling.

🚗 Stay safe on the roads:

Never drive through flood water
Reduce your speed
Increase your stopping distance
Be prepared for changing road conditions

Heavy rain can quickly lead to spray, surface water and sudden flooding, making driving conditions difficult and potentially causing road closures.

Before setting out, check your route and allow extra time for your journey. Keep an eye on Office for the latest weather.

25/08/2026
25/08/2026

Update on Ravine Road - We have been advised the work will now take place 26th of August (Wednesday) between the hours of
5:00 AM - 7:00 AM

Ravine Road
Aug 26 5:00 AM BST - 7:00 AM BST
JB400G-MAIN-A3-422021-01
Granted
North Yorkshire Council
Information for Road Users

Location
Ravine Road
Traffic management
Road closure
Date
Aug 26 5:00 AM - 7:00 AM
Work descriptions

Description
Patching takes place to repair the road surface, it involves removing a part of the surface around a pothole or defective surface course and placing a new patch of road surface. This is a cost-effective method to repair damage when a small area is affected. Patching works can be carried out in individual locations along a section of road, depending on the road condition .
Information for Residents

Contact North Yorkshire Council If you have an enquiry in respect of these essential highway works please contact us on 0300 131 2 131.
Our opening hours Mon and Tues 9am to 5pm; Wed 9.30am to 5pm; Thurs 9am to 5pm and Fri 9am to 4pm

Filey -  Road Closure - Aug 26 - Aug 28DescriptionNorth Yorkshire CouncilEssential highway maintenanceAN 422021 Ravine R...
24/08/2026

Filey - Road Closure - Aug 26 - Aug 28
Description
North Yorkshire Council
Essential highway maintenance
AN 422021 Ravine Road, Filey (From the toilets to the bridge) 26th August 2026
The Restriction will be in place for a period of 3 days between 26th August 2026 and 28th August 2026

The Road Restriction and any associated traffic management can be viewed using this URL link https://one.network/?tm=GB152077357

North Yorkshire Council

Taken yesterday when the weather was a little kinder!This Sunday(23rd) we have Lofthouse 2000 Brass Band playing on the ...
20/08/2026

Taken yesterday when the weather was a little kinder!

This Sunday(23rd) we have Lofthouse 2000 Brass Band playing on the bandstand 2pm while 4pm.

Address

52a Queen Street
Filey
YO149HE

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 5pm
Thursday 9am - 5pm
Friday 9am - 4:30pm

Alerts

Be the first to know and let us send you an email when Filey Town Council posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share