03/04/2026
The sun is shining, and progress continues steadily on site.
Block 1 is now fully leased, with tenants scheduled to move in throughout this month and next. The doors are numbered and ready.
In Block 2, hall carpeting is scheduled, and unit cleaning will begin shortly. Leases for this block are being finalized this week.
Block 3 is coming along very well. Flooring and cabinetry have been installed, final coats of paint are underway, and doors are being hung. This block is on track for completion by May 1st.
Work is also progressing in Block 4, where the in-floor heating system is operational and plumbing and electrical installations are ongoing.
Meanwhile, the Clubhouse is a hub of activity. Electrical work is being completed to prepare for upcoming inspections.
Arend continues to keep the site in top shape—doing what he does best: moving dirt and maintaining progress across the property.
We look forward to welcoming our first tenants soon!