09/01/2026
Five-Arches Bridge Rehabilitation Update and Temporary Park Closure (Sept. 2)
Lanark County Public Works reports the cap stones are now approximately 90% installed, and installation of the electrical conduits has begun. The northeast abutment has also been excavated to allow for construction of the new retaining wall. During excavation, crews uncovered what appears to be an old corduroy road, which may have served as the original approach to the original wooden bridge which was constructed in 1886.
Work on the bridge approaches, including grading and drainage improvements, will continue as scheduled. The temporary park closure remains planned for Wednesday, Sept. 2, to facilitate installation of electrical conduit beneath the park entrance. Advance notice and digital signage will continue to be used to inform the public of the closure.
Thank you for your patience!