18/05/2026
Works are progressing well at the Tooradin boat ramp, after construction kicked off a month ago.
The existing ramp has been removed to make way for a new and extended three-lane concrete boat ramp. Precast panels are on site and the team is getting ready to install, which will mark a key milestone in the project.
The upgrade works also include replacing the ageing pontoons with new longer pontoons, giving boaters more space to tie up, and a widened entrance to allow two-way traffic.
Dredging the toe of the ramp is expected to begin at the end of May, with works on track for completion in September 2026.
This project is made possible through the Victorian Government’s Better Boating Fund, which reinvests boaters’ licence and registration fees into improved facilities and programs for recreational boaters across the state.