03/06/2026
Project Update – May 2026
What’s Happened This Month
50m Pool
💧 Pool tiling 50% complete
💧 Rear grandstand wall blockwork installed
25m Pool, Amenities & Entry Building
💧 Completion of front of house building envelope, including final footings and flooring slabs, completion of structural & lightweight steel, and commencement of roof sheeting
💧 Services rough in commenced
💧 25m pool filtration works
Waterslides, Toddlers Pool & Splash Pad
💧 Toddler pool shell completed
💧 Water slide services installed
🔍What’s Next
Over the coming month, works will include:
💧 Continuation of 50m pool tiling, grandstand, plant room and Swim Club construction
💧 Installation of 50m pool shade sail columns
💧 Entry and amenities building services installation
💧 Continuation of pool filtration works
💧 Toddler pool & plant room construction
💧 Waterslide piers, foundations and base slabs
📸Spotlight Moment:
The pace of progress at the Denise Spencer Aquatic Centre has become even more visible over the past month, with the facility rapidly taking shape now that major underground and structural works are complete.
Comparing aerial images from the end of April to the end of May highlights just how quickly the site is transforming. In only a few weeks, the entry and amenities building envelope has been completed, including final foundation and flooring works, er****on of both structural steel and lightweight steel and significant progress of the roofing works. The 50m pool area has also visibly advanced, including pool tiling works over 50% complete, and the grandstand and surrounding structures taking shape.
What has largely been a structural construction site is now unmistakably becoming a recognisable aquatic facility for the community. As more of the building emerges above ground, the scale and layout of the centre can now be fully appreciated from above — an exciting sign of the momentum carrying the project forward.