๐ทโโ๏ธ Progress is happening beneath the surface... and now above it too!
The recent concrete pours are part of the ongoing pavement works through the central section of Todd Mall.
While much of the work completed so far has been happening underground - including new drainage, electrical and communications infrastructure - we're now starting to see more of the upgrade take shape above ground.
The new concrete forms part of the pavement construction, with new pavers to be progressively installed as each area is completed. ๐
Once finished, the upgraded pavement will provide a smoother, more accessible surface through the Mall, improving access to local businesses and helping create a space ready for the future.
Spare conduits are also being installed at key locations, making it easier to add future services with minimal disruption - meaning less need to dig up the new pavement down the track!