01/06/2026
Construction continued over the past few weeks as SEMSWA’s campus turf conversion project moves from initial earthwork into key stormwater improvements.
You'll notice that the first video (4/9) shows our preexisting concrete trickle channel, which has since been de-constructed and removed— this design change is an important step to help restore infiltration through the landscape rather than routing flows through a hardened feature.
In the second video (5/13), the site has been cut and fine graded, with most existing material exported, and you can also see the new concrete cross pans installed in SEMSWA's parking lot on the south and west sides of the swale. These features are designed to direct runoff into the swale, maximizing the amount of stormwater that can be slowed, filtered, and treated onsite.
Next, crews will place approximately 8 inches of amended topsoil within the swale to support healthy vegetation establishment—setting the stage for native, water‑wise planting in the coming phase.
We’ll continue sharing updates as the project progresses from construction to restoration and planting.