BEACH NOURISHMENT PROJECTS
Over the past 25 years, the Town has completed 24 nourishment projects that have placed a total of 5,249,983 cubic yards of sand on the beach.
Over half of that amount came from two major projects: 1) Central Reach in 2017 which placed 1,430,000 cubic yards; and 2) the FEMA project in 2022 which placed 1,655,000 cubic yards.
The 25-year average is 210,000 cubic yards of sand per year. At $20/cubic yard, this would equate to an annualized cost of $4.2M.
The Town’s share of past project costs has ranged from zero for the FEMA project, to 25% for dredging projects, to 100% for Central Reach.
When planning for future projects, the biggest variables are the cost of sand per cubic yard and the Town’s share of the total cost.
Obviously, the biggest unknown is whether or not we will get hit by a major storm.