04/12/2024
JICA Expert Team (JET) started 9th activity from 28th October 2024 in Faisalabad. Project Implementation Unit (PIU) of WASA-F and JET had 18th weekly meeting at WASA-F head office on 11th November.
With support from JICA Expert Team (JET), WASA-F proceeds to improve water supply services in two priority areas by implementing hydraulic separation in water distribution pipeline construction. In Madina Town where the construction finished, water pressure checks were conducted in each house on November 20th. It was confirmed that higher water pressure than before was maintained during water supply hours and residents expressed their thanks. Currently, water charges are flat-rate tariff system but will change to a metered tariff system once the water meter installation work is completed. WASA-F aims to increase its water collection rate, increase its customer number, and improve its management by improving its water supply service and changing to the metered tariff system.