Ministry of Public Works-Republic of Liberia

Ministry of Public Works-Republic of Liberia Statutory Authority: (Government of Liberia Engineering Arm) - Summary of Agency in Liberia at this time:

The Ministry of Public Works is a highly rated Public Sector Agency spearheading the construction and reconstruction of Liberia's roads and other infrastructures.

18/08/2026

Pavi Fort Concession Inaugural Steering Committee Meeting Held @ the Ministry of Public Works

Highlights from Minister R Layfette Giddings' Tour:1. Inspection of the Japan Freeway extension spanning Freeport to Gab...
06/08/2026

Highlights from Minister R Layfette Giddings' Tour:

1. Inspection of the Japan Freeway extension spanning Freeport to Gabriel Tucker Bridge

In a conversation with Minister Giddings during the tour, the Project Engineer explained that the median of the existing road is being removed and temporarily paved to enhance vehicular traffic during the impending sectional construction that should begin immediately in the dry season. This exercise has almost been completed as the remaining portion is less than five-hundred meters in length.

The Minister and his team also carried out a full inspection of the contractor's Camp Site at Star Base. During the exercise, the team confirmed the full completion of the camp site with standard soil and concrete labs, equipped with state-of-the-art machines. More still, the contractors displayed the massive molding of cross & side drains culverts in preparation for full construction works. They assured the Minister that all of the culverts needed for the project will be completed latest September of this year, while reaffirming their commitment to Liberia's development.

2. Inspection of Freeport-St. Paul Bridge Corridor

In spite of the rain that most times disrupts normal work activities, the contractors have made significant gains by constructing the side drains up to Point-Four Junction, creating proper channels for the free flow of water upon full completion of the road. In some sections, especially between Kuwait to St. Paul Bridge, soft lands were dug and filled with borders as a stabilization method to get the soil ready for pavement.

Interestingly, MDMC has adopted a more different engineering approach by avoiding the application of laterite; instead, they are using aggregate to form the sub-base and base sources. According to the Project Engineer, this method is being used based on the low soil quality. Their analysis showed that using laterite will only provide a temporary solution to the problem of soil instability, which has been a major factor causing constant deterioration of the road.

3. St. Paul Bridge-Clay Junction (Pavi Fort Concession)

Inspection began from the contractor's Camp Site with the goal of counter-checking the agreed terms of the concession. Interestingly, the Contractor's Concrete Bashing Plant has been completed and fully operational. They have aquired a quarry from whence aggregate would be sourced to form the base course and facilitate other concrete and asphalt works. The staff and consultants' quarters are nearing completion.

Most importantly, Pavi Fort has cleared more than twelve kilometers and begun the construction of crossed-drains in some sections of the road. Additionally, there are some areas when borders were applied for soil stabilization.

4. New Georgia Estate Road

Being constructed by Quality Group of Companies, the road has gone through major design modifications, which has caused basic delays. These modifications are strictly intended to ensure that the right things are done during the construction process.

However, the Ministry and the contracting firm have found a midpoint, a model through which New Georgia Estate Road will be constructed with the required standard that meets public expectations.

5. Chicken Soup Factory Road

More than just an inspection, the Chicken Soup Factory road underwent a physical audit to ascertain progress, which ultimately forms the basis for payment of the constrator.

During the process, Minister Giddings praised the ongoing works. The team confirmed that a total of 1.5 kilometers of rigid pavement has been done. This, Minister Giddings termed as one that signals a significant milestone in connecting feeder roads to primary roads.

6. Paco & Peace Island road connecting Alison Street and Ministerial Complex.

Although the corridor has experienced temporary closure out of safety concerns, the team drove through to check a few things:

✔️ Construction of box & circular culverts
✔️ Stabilization of Applied Borders in wet areas
✔️ Safety of the ridding surface
✔️ Evaluation of the possibility to reopen the corridor to vehicular traffic

05/08/2026

Official Closing of the Liberian-Swedish Access Driven Rural Development Program (Village Access Roads)

04/08/2026

Minister R Layfette Giddings sits on OK-FM to shed light on the Gbarnga-Salayea Road Dedication, as well as the Salayea-Konia/Zorzor-Yeala Groundbreaking

President Boakai Dedicates Gbarnga–Salayea Road, Breaks Ground for Two New Corridors at Historic Bartuah CeremonyJuly 28...
28/07/2026

President Boakai Dedicates Gbarnga–Salayea Road, Breaks Ground for Two New Corridors at Historic Bartuah Ceremony

July 28, 2026
Bartuah, Lofa County

President Joseph Nyumah Boakai on Tuesday formally dedicated the newly completed Gbarnga–Salayea road, marking the end of a construction journey that stretched nearly a decade and tested the patience of communities across B**g and Lofa Counties. At a separate ceremony held at Salayea, President Boakai broke ground on two new road projects: the Salayea–Konia corridor and the Zorzor–Yeala corridor, signaling the government's intent to press forward with expanding the country's road network into Liberia's northern belt.

The dedication drew the Vice President, the Deputy Speaker and Members of the Legislature, representatives of the international financing partners who backed the project, officials of the Ministry of Public Works, and residents from surrounding towns and villages along the corridor who turned out to witness the milestone.

The 81-kilometer road, which is part of the larger Gbarnga–Voinjama–Mendikorma road project, connects Gbarnga in B**g County to Salayea in Lofa County. The contract for the civil works was awarded to China Henan International Cooperation Group (CHICO) after a Letter of Acceptance was issued in mid-December 2017, with the Works Contract signed the following day. Mobilization began in late January 2018, and the project reached effective commencement in June 2018 under an original 36-month timeline that targeted completion by May 2021.

That timeline did not hold. MPW acknowledged that a combination of challenges forced the project's completion date back by roughly five years. The road suffered two suspensions of works, which, in-turn, triggered two rounds of contract extensions.

The first extension, covering 26 months plus a Defects Liability Period, ran from June 2021 through July 2024. A subsequent 20-month extension of time, effective August 2024, carried the contract through March 2026, before a second formal Contract Extension pushed the timeline through March 2027 to accommodate a Defects Liability Period running from April 2026. By July 2026, the project had been under implementation for 99 months; well over eight years from its effective start.

Speaking to the delay, Minister Roland Layfette Giddings pledged that the Ministry of Public Works will work to prevent a similar pattern of repeated extensions on the upcoming Salayea–Konia project.

The financial picture grew alongside the timeline. The contract's value, originally set at roughly US$40.86 million, climbed to approximately US$51.98 million once approved variations of just over US$7 million and the two time extensions were factored in. The related consultancy services contract, covering design review, bidding document preparation, and construction supervision by SaudConsult in partnership with TSC Engineering and Construction Consultants, Inc., also grew to roughly US$3.70 million.

Throughout implementation, the Ministry of Public Works Infrastructure Implementation Unit served as the government's implementing authority, coordinating between the central administration, the consultants, and CHICO as the works contractor.

Much of the ceremony's tone centered on gratitude toward the road's multi-donor financing consortium, whose backing carried the project through years of delay. The financing structure comprised the Arab Bank for Economic Development in Africa (13.34 percent), the Kuwait Fund for Arab Economic Development (24 percent), the OPEC Fund for International Development (31.02 percent), and the Saudi Fund for Development (31.64 percent), with the Government of Liberia contributing counterpart funding that covered resettlement action plan implementation, duty waivers, and other obligations.

Giving Special Remarks, President Joseph Nyumah Boakai averred that the completion of the project represents the Liberian Government's commitment to improving infrastructure. The President cautioned citizens of B**g and Lofa counties to protect the investment in every way possible, adding that infrastructure development is only sustainable when those it affect see the protection of it as a primary responsibility.

In what could be termed as a comprehensive overview of the project, Minister Giddings extended thanks to the visiting delegations representing the financing partners, framing the project as a demonstration of sustained international cooperation with Liberia's road sector; one that endured despite the project's complications and near-decade timeline.

“The pavement itself was built up from an engineered sub-grade, a 250-millimeter granular sub-base, a 200-millimeter crushed-stone base course, and a 50-millimeter asphalt concrete wearing course; a structure designed to withstand projected commercial and passenger traffic volumes, including cross-border freight”, the Minister lamented.

Finance Minister Augustine Kpehe Nganfuan delivered a rather thrilling historical rendition of how the project began in 2010, when he was Minister of Finance during the regime of former President Ellen John-Sirleaf. He furthered that it was President Joseph Nyumah Boakai who handed the Finance Minister's delegation the original design of the road done in 1989, and asked them to take it along hoping that they could secure financing for the project.

Finance Minister Nganfuan disclosed that he was glad to have led the final delegation to Kuwait to resume talks for the partners to return with their support.

The partners expressed appreciation to the Government of Liberia for its demonstrated commitment to infrastructure development. They pledged to continue to work with the Government to connect households with basic social services that are essential to every day life.

28/07/2026

President Boakai Dedicates Gbarnga to Salayea Road; Breaks Ground for Salayea to Konia, Zorzor to Yeala..

PRESS STATEMENTA New Artery for Liberia's North; As President Boakai Dedicates Gbarnga—Salayea Road27 July 2026Monrovia,...
27/07/2026

PRESS STATEMENT

A New Artery for Liberia's North; As President Boakai Dedicates Gbarnga—Salayea Road

27 July 2026
Monrovia, Liberia

On Tuesday, July 28, 2026, President Boakai will formally dedicate the completed 81-km Gbarnga–Salayea highway and launch construction on two further stretches: the 50-km Salayea–Konia and 6-km Zorzor–Yeala roads. The ceremony is scheduled to take place at the B**g–Lofa border.

The event caps a $72.8 million financing push from the OPEC Fund, BADEA, and the Kuwait Fund, with the Saudi Fund separately committing to pave the final 64-km Konia–Voinjama stretch, completing a corridor that links B**g and Lofa counties all the way to the Guinean frontier.

Ahead of the event, Public Works Minister Roland Giddings has confirmed that construction activities are expected to begin this coming dry season, with the projects expected to generate substantial local employment.

The Gbarnga—Salayea road is expected to enhance year-round travel between Gbarnga and Salayea, ending the rainy-season isolation that once cut communities off. It will also serve as a cheaper route for the transportation of farm to market produce.

Meanwhile, completing the additional two stretches will connect Voinjama to Gbarnga, as well as enhance crossed border trade between Liberia and Guinea while at the same time promoting regional integration..

Address

South Lynch Street, Opposite Antionette Tubman Stadium (ATS)
Monrovia
P.O.BOX9011

Opening Hours

Monday 09:00 - 17:00
Tuesday 09:00 - 17:00
Wednesday 09:00 - 17:00
Thursday 09:00 - 17:00
Friday 09:00 - 17:00

Telephone

+231770299007

Alerts

Be the first to know and let us send you an email when Ministry of Public Works-Republic of Liberia posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organization

Send a message to Ministry of Public Works-Republic of Liberia:

Shortcuts

Share