06/02/2026
Last week we discussed what happens during a shakeout, this week we’re going to talk about when we start to erect the structure. Once the shake out is complete and every piece is accounted for, the real magic begins. 🏗️
The tapered columns go up first, these are the backbone of the entire structure. Once they’re plumbed, squared, and secured, the crane or hoisting machine (tele-handler pictured) starts lifting the rafter sections into place, connecting column to column and forming the structure of the building.
What you’re seeing in this photo is exactly that. A rafter section being raised and guided into position while our installers work from the manlift to bolt up the connection. Every connection matters. Every lift counts.
This is where a steel building starts to take shape. 🔩⬆️